Wednesday, August 14, 2013

Green and Tee Construction Update

Work is progressing nicely on #10 and #13 greens.  The weather has been perfect!  If all goes well we might be seeding the greens by the end of next week.  We are continuing to rebuild flood damaged tees and hope to have that finished by next week as well.  We are now beginning the renovation of the rough and as the tee and green construction ends, we will restore the rough in those areas damaged by construction and flood.


Jeff Hollembeak (builder), Greg Martin (Golf Course Architect) and Jim Vande Logt (Green Chair)


Final grading of the base.  The base will mirror the surface of the green.  The next step is adding drainage, pea gravel then 12" of mix.


GPS maps of the old and new #13 green.  The new will be about 200 sqft larger.


Seeding the newly renovated rough area behind #1 green.  Next step hydro mulch.


#11 Men's and Pro tee are complete. We will be raisng the ladies tee.


Finial phase of work on #2 mens and ladies tee.